risk question

 Being the project manager in a high-risk electronics project with a lot of new 

technologies, you developed a risk management plan and identified risks which 
you documented in a risk register. Then, the risks were analyzed and response 
planned.
It is getting obvious during risk monitoring and control meetings that the 
documents you created are not very helpful. What have you probably done 
wrong?
o You failed to use an RBS.
o You did the first processes alone.
o You did not identify Triggers.
o You did not calculate EMVs.
admin's picture

 Since the question says that documented risks are not very helpful, I would go with option C.

However if the question said that documented risks are not the real risks, then I would go with option A.