 Q4 Question : Matrix organizations exhibit features of both projectized and functional organizations. In a Weak Matrix organization, the role of a project manager is that of a:

1. coordinator and expediter

2. project manager with considerable authority

3. support person

4. functional manager

 

4. Correct Choice: 1

Justification: Weak matrix organizations maintain many of the features of a functional organization and the project manager role is more that of a coordinator or expediter than that of a manager.

1. coordinator and expediter