Please explain this question
Submitted by kan3 on Thu, 08/04/2011 - 20:21
Hello,
Can anyone please explain this question,
http://oi54.tinypic.com/qps7rs.jpg
How will the project finish sooner if Activity F finishes immediately? Won't there be another critical path?
Start-C-D-E-B-Finish?
Thank you.
Forums:


hsingh78
Fri, 08/05/2011 - 12:48
Permalink
I think since now the
I think since now the critical path is shared on the activity F path, so it makes sense to say that the project will finish soon if activity F will finish sooner. Although the wording of the answer is questionable. (The rest 3 options any way are wrong)