Confused - calculate EAC and VAC
Submitted by pmpSGI on Tue, 06/28/2011 - 19:56
Information provided -
BAC=500, ETC=200, PV=500, AC=200, EV=300, CPI=15.
Situation 1. The type of variances that have occured are believed to be atypical, and these variances are expected to continue.
Situation 2. The variances are typical and do not expect these variances to continue.
Calculate VAC for the project in both situations.
Can someone please explain how to calculate VAC in both cases. Appreciate a quick response as I go for test tomorrow. Seems my brain is fried if I can't apply formulae to questions :(
Thanks!
Forums:


PMPBOY
Tue, 06/28/2011 - 20:19
Permalink
My bet VAC will be 100 for atypical and 286.66 for typical
Situation 1. The type of variances that have occured are believed to be atypical, so
following formula will apply:
EAC = AC + BAC - EV = 200 + 500 - 300 = 400
Then VAC = BAC - EAC = 500 - 400 = 100
Situation 2. The variances are typical so apply the following formula:
EAC = AC + (BAC - EV) / CPI = 200 + [(500 - 300) / 15 ] = 200 + 13.34 = 213.34
Then VAC = BAC - EAC = 500 - 213.34 = 286.66
aaron
Tue, 06/28/2011 - 20:31
Permalink
These are the formulaes you
These are the formulaes you should know about
Forecasting formulas