Frustrated about this question about Power: Expert vs Formal
I am memorizing the types of power based on this diagram:
https://image.slidesharecdn.com/26b3e160-1ed4-4613-9445-9410ae8aa60f-150...
The easy way I remember is that formal and reward are the best for compliance, expert and reverent are the best for commitment.
In this question:
You are a project manager leading a cross-functional project team in a weak matrix environment. None of your project team members report to you functionally, and you do not have the ability to directly reward their performance. The project is difficult, involving tight date constraints and challenging quality standards. Which of the following types of project management power will likely be the MOST effective in this circumstance?
A. Referent
B. Expert
C. Penalty
D. Formal
The official answer is:
Reward and expert are the best sources of power. Reward is not listed as a choice.