Scope change or Scope Enhancement?
Submitted by Dr. Morpheus on Tue, 12/06/2016 - 09:08
Hi,
I am working on a project for software, We have recieved new addition to the scope of existing undergoing project, what we can give it more sophisticated name?
Scope Change? Change Scope? or any better business name to fill the documents?
Thanks
Forums:


admin
Thu, 12/29/2016 - 14:31
Permalink
Scope increase or
Scope increase or requirements modification
Basically its for the client to understand that they have to pay extra for additional work.
jyotig
Fri, 12/30/2016 - 05:55
Permalink
Change management
http://www.izenbridge.com/videogallery/webinar-on-integrated-change-mana...
pmalik
Tue, 01/03/2017 - 07:52
Permalink
Change Management
Change
A Change is any modification to any Plan, Document, Work Product, Deliverable or Artefact. It needs an approval from CCB before it can be implemented.
Change Management
A Process where Changes are identified, documented, analyzed and decided (approved or rejected). It is usually unique to an Organization. Many organizations used manual and automated tools for Change Management.
To understand more about change and change management, you can read following articles:
1. Change Management Definition
2. Differences Between Configuration Management vs Change Management
3. 9 Rules to Answer PMP Change Management Questions