I have added one more Free PMP practice exam today
http://thecertschool.com
anurap
Sat, 10/31/2015 - 16:24
Permalink
You are working with word processing Project and currently the Cost Performance Index is 1.6 and Earned Value is $25,000 what is Actual Cost?
Correct Answer is: 15265
CPI= EV/AC , 1.6=25000/AC AC=25000/1.6 ==> 15265
Please correct it.
manik_suriya
Sat, 10/31/2015 - 18:28
Corrected thanks a lot for ur feedback
anurap
Sat, 10/31/2015 - 16:24
Permalink
Feedback on Quiz#1
You are working with word processing Project and currently the Cost Performance Index is 1.6 and Earned Value is $25,000 what is Actual Cost?
Correct Answer is: 15265
CPI= EV/AC , 1.6=25000/AC AC=25000/1.6 ==> 15265
Please correct it.
manik_suriya
Sat, 10/31/2015 - 18:28
Permalink
Thanks
Corrected thanks a lot for ur feedback