Hello all,
I have a question regarding figure 7-9 in PMBOK, which is the cost baseline including the funding requirements.
It shows the BAC and on top of it, the managment reserve.
So, what I don't understand is the wording.
Budget is cost baseline + managemnt reserve.
Does this not apply for BAC? Is BAC considering only the cost baseline?
Or is project budget = cost baseline + managemnt reserve?
Please clarify this for me, thanks!
Forums:


Vishwanath
Tue, 08/26/2014 - 12:07
Permalink
Hi
Hi,
Cost Budgegt = costbaseline + management reserve
Regards,
Vishwanath