Question on planned value

Task A is worth $200, is 100% complete, should have been done on day 1, and actually cost $200. Task B is worth $75, is 90% is complete, should have been done on day 2, and actually cost $ 120 so far. Task C is worth $ 200, is 75% complete, and should have been done on day 3, and has cost $ 175 so far. The total budget is $ 1000. what is the planned value as of day 2?

1.275
2.-417.5
3.495
4.-275

What is the answer?

So easy.

275

PV TASK1 + PV task 2

200 (PV =BAC at completion) + 75 (what should be achieved at day 2)