Project Selection Quesion

Generaly, Project managers are.....................................for project selection


Informed
Responsible
Consulted
Accountable


 


 


I vote for Informed

 I m not sure from which site you got this question. Please be aware that some of the free questions available online does not match pmp standarads

Definetaly it's informed when the project manager is hired after the project is selected.buit after that he is accountable for the project success and failure.


So this question should stated that project manager is hire before the project is selected or just after that.sometimes project manager can take part (role) in the project selection process, so that answers depends on the condition (scenario).


 


Arif Kamran