WBS
Submitted by kiranu23 on Sun, 08/29/2010 - 19:49
A project team is in the planning stage and they have completed creating Work breakdown structure for the project. Which of the following process can they start NEXT? |
| Options: |
| A. Define Activity |
| B. Estimate Cost |
| C. Determine Budget |
D. All of the above What should be the answer. The source says D, which I feel is incorrect, and my answer is A. Any thoughts??? |
Forums:


pkukilla
Sun, 08/29/2010 - 20:06
Permalink
It should be define activity
It should be define activity