probability question - Please explain
Submitted by sai_murthy on Fri, 07/30/2010 - 05:04
Question:
Can you please explain me how the answer is 99.73%
An activity has an optimistic estimate of ten days, pessimistic estimate of sixteen days,
and most likely estimate of thirteen days. Assuming a normal distribution,
what is the probability that the task will be completed within 10 to 16 days?
99.99 %
99.73 %
95.46 %
68.26%
Ans : 99.73%
Forums:


jagjitdhaliwal@...
Fri, 07/30/2010 - 06:41
Permalink
Hi Sai,With P = 10, M = 13
Hi Sai,
With P = 10, M = 13 and O=16, the EAD can be calculated to come as 13.
So, the deviation in duration 10 to 16 days from mean(13) is +/-3. Since it's 3-sigma, % of occurances to fall between two control limits is 99.73%.
Could you please share source of question as I think question is bit vague. Anyway, I assume above as reasoning for answer.
Regards,
Jagjit
sai_murthy
Fri, 07/30/2010 - 07:07
Permalink
Probablity
Thank you Jagjit.
For the explanation. Soruce is PMStudy.com
jagjitdhaliwal@...
Sat, 07/31/2010 - 18:17
Permalink
Hi Sai,Came across following
Hi Sai,
Came across following link which I think explains the reasoning better than mine.
http://www.youtube.com/user/SirGanttalot
Regards,
Jagjit
sai_murthy
Sat, 07/31/2010 - 21:56
Permalink
Jagjit You are correct. Mean
Jagjit
You are correct.
Mean = Most Likely = 13
In PERT we do probabilistic estimation ,
PERT Sigma (Standard Deviation) = (Pessimistic - Optimistic)/6 ...... See the formula given in Quality KA under Standard Deviation slide
= (16 - 10)/6 = 1
Probability to be 99.73% means 3 Sigma Control limit
UCL = Mean + 3*Sigma = 13 + 3*1 = 16
LCL = Mean - 3*Sigma = 13 - 3* 1 = 10