How to determine which activity to shorten?
activity preceding activity duration in weeks
start none 0
A start 1
B start 2
C start 6
D A 10
E b,c 1
F C 2
G D 3
H E 9
I F 1
End G,H, I 0
If you needed to shorten the duration what activity would you try to shorten?
A. Activity B
B. Activity D
C. Activity H
D. Activity C


cnppmp
Wed, 06/19/2013 - 03:10
Permalink
The activity on critical path
The activity on critical path in network diagram because the non-critical path activity do not have impact on the duration s long as the critical path remains same.
Regards CN Patil
vishalpratap
Wed, 06/19/2013 - 04:10
Permalink
so is it H
so is it H
tpmason1908
Wed, 06/19/2013 - 04:30
Permalink
C
Activity C is the answer
vishalpratap
Wed, 06/19/2013 - 06:35
Permalink
If both are on critical path
If both are on critical path then how to decide
sanskrit
Thu, 06/20/2013 - 13:14
Permalink
If both are on critical path then Activity that comes FIRST
If both are on critical path then Activity that comes FIRST should be the one one to shorten
ma498
Wed, 06/19/2013 - 06:40
Permalink
need explanination
Could someone explain the answer in bit detail, as this seesm to be intresting question, also refer material for studies for similar kind of situations
sanskrit
Thu, 06/20/2013 - 13:15
Permalink
If both are on critical path then Activity that comes FIRST
If both are on critical path then Activity that comes FIRST should be the one to shorten