enhance opportunities and reduce threats
Submitted by vijayavadrevu on Wed, 05/29/2013 - 12:40
1) You have completed the process of developing options and actions to enhance opportunities and to reduce threats to project objectives. What is your NEXT step?
- Determine which risks may affect the project and document their characteristics.
- Implement risk response plans, track identified risks and monitor residual risks
- Define how to conduct risk management activities for a project.
- Assess the priority of identified risks using their probability of occurrence
Forums:


sanskrit
Wed, 05/29/2013 - 12:46
Permalink
Option 2
Option 2 i.e Implement risk response plans, track identified risks and monitor residual risks
jvleminc
Wed, 05/29/2013 - 12:56
Permalink
2
Option 2, by simple elimination. Developing options and actions and enhance opportunities -> Plan Response
1: Should already have been done in Identify risks, before planning the responses,
3: Should already have been done when preparing Risk Management plan
4: Happens in Quantity/Qualify risks, before planning the responses,
cnppmp
Wed, 05/29/2013 - 15:12
Permalink
It is the definition of Risk Response plan?
Option 2?
Regards
CN Patil
vijayavadrevu
Wed, 05/29/2013 - 15:17
Permalink
Yes, option 2 is right with
Yes, option 2 is right with the explanation given by @ jvleminc