Your hardware vendor left you a voicemail saying that a snowstorm in the Midwest will
prevent your equipment from arriving on time. You identified a risk response strategy for
this risk and have arranged for a local company to lease you the needed equipment until
yours arrives. This is an example of which risk response strategy?
A. Transfer
B. Acceptance
C. Mitigate
D. Avoid


thevoyager
Fri, 05/17/2013 - 13:32
Permalink
mitigate
Mitigate
crushPMP
Fri, 05/17/2013 - 14:20
Permalink
C?
C?
BK
Fri, 05/17/2013 - 14:53
Permalink
Yes. C is correct.
Yes. C is correct.