Work Package Vs Control Accounts
Submitted by sanskrit on Fri, 05/10/2013 - 13:12
There were two Questions in two differents books , With diffennt Options
A. At what level the scope, cost, and schedule are integrated and compared to the earned value for performance measurement.
- Control Account Level
- Work Package Level
- Activity Level
B. At what level the scope, cost, and schedule are integrated and compared to the earned value for performance measurement.
- Work Package Level
- Activity Level
Forums:


crushPMP
Fri, 05/10/2013 - 14:31
Permalink
A. 1 - Control Account level
A. 1 - Control Account level for management
B. 1 - Work Package Level?