Process Groups overlap question
Submitted by Jgrind07 on Thu, 05/09/2013 - 05:26
While the five process groups are typically completed in order, they often overlap with each other throughout the project. Which two process groups should never overlap unless a project is canceled?
A. Initiating and Closing
B. Initiating and Executing
C. Initiating and Monitoring and Control
D.Planning and Closing
What is your choice and why?
Thanks
Jai
Forums:


sspawar
Thu, 05/09/2013 - 05:47
Permalink
Afig 3-2
A
fig 3-2
rwmv
Thu, 05/09/2013 - 05:57
Permalink
Answer-A
OPTION A
crushPMP
Thu, 05/09/2013 - 14:49
Permalink
Definitely A
Definitely A
Jgrind07
Thu, 05/09/2013 - 15:34
Permalink
Yes, Its A. I came across
Yes, Its A. I came across this question and felt intresting so wanted to share it with others.
Thanks Pawar and CrushPMP
Jai