organization structure -- type
Submitted by vijayavadrevu on Mon, 05/06/2013 - 16:49
You are managing a complex project which requires some highly skilled resources on embedded design. You obtain these resources from the organization pool. You specify the duration for which they would be required. Once your project activity is complete, you need to free these resources for reassignment. You are working in which kind of organization structure?
A)Functional
B)Projectized
C)Matrix
D)Tight Matrix
Forums:


crushPMP
Mon, 05/06/2013 - 16:59
Permalink
C?
C?
vijayavadrevu
Mon, 05/06/2013 - 17:08
Permalink
You are right? Why not
You are right? Why not Projectized?
crushPMP
Mon, 05/06/2013 - 17:11
Permalink
I would say, I was split-even
I would say, I was split-even between B and C and eventually decide to go with C.
The situation describes the mix of both Projectized (You are managing a complex project ) and Functional (You obtain these resources from the organization pool. You specify the duration for which they would be required. Once your project activity is complete, you need to free these resources for reassignment)
vijayavadrevu
Mon, 05/06/2013 - 17:14
Permalink
Thank You for the
Thank You for the explanation
rwmv
Mon, 05/06/2013 - 17:45
Permalink
Answer-C
The keyword for me was the Free the RESOURCES for REASSIGNMENT. Its definitely not projectized nor function- coz in functional they work their day work and the project. so its Matrix.