some questions
Submitted by abdsal on Tue, 04/30/2013 - 04:59
There are some questions below. Pls answer with explanation.
1. All of following should be done by the project manager during project control EXCEPT?
A) Determine that a change has occurred
B) Ensure that a change is beneficial
C) Make sure all changes are approved by management
D) Manage changes as they occur
2.As a project manager, you have been given responsibility for a project that is behind
schedule. Which of the following is the MOST appropriate technique to compress the project
in order to meet the original target date and budget?
A) PERT
B) Redo the plan
C) Crashing
D) Fast tracking
3. You have been assigned to manage a portion of a larger project that is supposed to be
finished within a two-week period. You have met with the leadership of the area to gather
requirements, and you have a project charter, scope statement and project plan that have been
approved by these individuals. You are told to meet with the actual user of the results of the
project to demonstrate how the system will work. When you give the demonstration, it is
clear that the user's requirements are very different from the ones you were initially given and
to which both you and the client agreed. What is the BEST thing for you to do now?
A) Generate a change request for the user's requirements
B) Convene another meeting with the leadership of the area and the user to generate a revised
set of requirements
C) Attempt to meet as many of the user's requirements as possible within the project's
established budget and schedule
D) Complete the work as originally specified and formulate a new project to meet the user's
requirements
Forums: