Need help with understanding when to apply...
Submitted by rwmv on Thu, 05/16/2013 - 08:30
Hi folks,
Need help in understanding when to apply which formula, especially the following:
EAC ‘no variances’ = BAC / CPI
EAC ‘fundamentally flawed’ = AC + ETC
EAC ‘atypical’ = AC + BAC - EV
EAC ‘typical’ = AC + ((BAC - EV) / CPI)
ETC = EAC - AC
ETC ‘atypical’ = BAC - EV
ETC ‘typical’ = (BAC - EV) / CPI
ETC ‘flawed’ = new estimate
Forums:


BK
Thu, 05/16/2013 - 09:19
Permalink
http://www.deepfriedbrainpro
http://www.deepfriedbrainproject.com/2009/09/estimate-at-completion-eac-earned-value.html
cnppmp
Thu, 05/16/2013 - 19:15
Permalink
EAC ‘no variances’ = BAC /
EAC ‘no variances’ = BAC / CPI
when cost variances continues.
EAC= BAC/SPI
when schedule variance continues.
EAC ‘fundamentally flawed’ = AC + ETC
In case of re-baselining
EAC ‘atypical’ = AC + BAC - EV
whatever has happened, project will be on budget.
EAC ‘typical’ = AC + ((BAC - EV) / (CPI*SPI)
when both cost and schedule performances are considered.
regards
CN Patil