1.your company has a projectized org structure--as your prj nears completeion you notice that ur team members are more interested in finding new positions rather than properly discharging theri duties
their motivation is
safety
social
psychological
self esteem
answer is safety : can some one explain i chose self esteem
===========================================
2 you are in the execution stage of the project. for the information of stakeholders you ahve documemts to highlight project status .ll and issue logs and outputs from other KA.these documents shud be included in?:
project reports
change logs
ll doc
performance reports
answer is project reports where as i chose performance reports.
can you explain


admin
Wed, 10/15/2014 - 03:33
Permalink
1. They are looking for
1. They are looking for safety as after the project they are trying to find another job so in case of any policy changes like firing they are spared.
Correct word would be security or Job Security.
2. Performance report is work performance information and will not have stakeholder details.