Is my calculation for EAC correct?
Submitted by y0zh on Wed, 05/08/2013 - 07:35
You are assigned as the project manager to a project which had a one-time cost variance in the past caused by unexpected rework which has meanwhile been finished.
You perform earned value analysis and get the following results:
EV: 250,000; PV: 200,000; AC 275,000
BAC is 500,000.
What is EAC?
BTC=BAC-PV=500,000-200,000=300,000
lapse=PV-EV=-50,000
EAC=AC+BTC+lapse=275,000+300,000-50,000=525,000
Forums:


rwmv
Wed, 05/08/2013 - 08:28
Permalink
EAC formula
Estimate at Completion= Actual cost + (Budget at Completion-Earned Value)
EAC- AC+(BAC-EV)
275000+(500,000-250,000)
EAC=275,000+250,000
EAC= $525,000
y0zh
Wed, 05/08/2013 - 08:48
Permalink
Thanks,is BTC something old
Thanks,
is BTC some old stuff for PMBOK? Why we can't use below formula EAC = BTC + lapse + AC
-------------------------------------------------
Your project exceeded costs in the past caused by an underestimation of resource costs in the cost baseline:
PV: $1,200,000, EV = $1,000,000, AC = $1,200,000
You expect the underestimation to influence the future as much as it did in the past.
If the BTC (Budget to Complete) is at $1,000,000, what should be your new EAC (Estimate at Completion)?
A. $1,800,000
B. $2,000,000
C. $2,200,000
D. $2,400,000
Answer:
You know your Actual Cost $1,200,000 and Budget To Complete $1,000,000, and you also know that your baseline has a lapse = PV - EV = $1,200,000 - $1,000,000 = $200,000 (you wouldn't have that if estimated properly, right?). So, Estimate at Completion now would be an amended value of the expected cost of completing project work plus the actual cost.
So, EAC = BTC + lapse + AC = $1,000,000 + $200,000 + $1,200,000 = $2,400,000
BK
Wed, 05/08/2013 - 14:16
Permalink
Not sure about BTC though,
Not sure about BTC though, in this case formula used should be
EAC= AC+ BAC-EV
as the future variance is atypical from the present.