If P=18, O=8 and M=15 then result is 14.333. In this situation what is the correct answer? 14 or 15?
PMP Lite Mock Exam 17 by Christopher Scordo says answer is 14.
As this estimate process is based on uncertinity and risk so we should take celling value so my choice is 15.
Please correct me if I am wrong.
sspawar
Mon, 09/17/2012 - 03:03
Permalink
This is universal norm
<0.5 = 0
>0.5 = 1
if you are rounding off any decimal data/figure
after all it is estimate
and it is not your own business
follow the principles
risk may happen at passimistic too
sahbabu
Mon, 09/17/2012 - 14:34
Thanks
sspawar
Mon, 09/17/2012 - 03:03
Permalink
This is universal norm<0.5
This is universal norm
<0.5 = 0
>0.5 = 1
if you are rounding off any decimal data/figure
after all it is estimate
and it is not your own business
follow the principles
risk may happen at passimistic too
sahbabu
Mon, 09/17/2012 - 14:34
Permalink
Thanks
Thanks
sahbabu
Mon, 09/17/2012 - 14:34
Permalink
Thanks
Thanks