Math qns_need help
Submitted by BK on Fri, 04/19/2013 - 10:04
I need some help on math related qns, do we have any url/link where I can found all math related qns for
Practice. Also finding difficulty for EVM related qns, like I am struggling when choosing EV/CV/EAC/BAC etc
From the wording of the qns. I have remembered all formula from Nair’s note (cheat sheet)
Pls provide some guidance.


BK
Fri, 04/19/2013 - 10:54
Permalink
Btw this is the formula
Btw this is the formula list, I remembered
CV = EV - AC
CPI = EV / AC
Formula for TCPI to meet the BAC is: TCPI = (BAC-EV) / (BAC-AC)
Formula for TCPI to meet the EAC is: TCPI = (BAC – EV) / (EAC – AC)
SV = EV - PV
SPI = EV / PV
VAC = BAC – EAC
ETC = EAC - AC
ETC ‘atypical’ = BAC - EV
ETC ‘typical’ = (BAC - EV) / CPI
ETC ‘flawed’ = new estimate
EAC ‘atypical’ = AC + BAC - EV
EAC ‘typical’ = AC + ((BAC - EV) / CPI)
EAC ‘fundamentally flawed’ = AC + ETC
EAC ‘no variances’ = BAC / CPI
zubair.raja
Fri, 04/19/2013 - 15:27
Permalink
Try this
Try this out:
http://www.scribd.com/doc/28680971/101-PMP-Sample-Questions-for-the-PMP-Exam
101 mathematical questions, covering, Earned Value, Forecasting, Procurement, Time related and project selction methods etc... Excellent source