Hi, 
I came across a question in pmstudy which asked: what is the last activity in project closing and the answer said "Release resources". But there was a similar question in exam central with choices like "release resources assigned to project", "close procurements" and the answer said "Close Procurements" here. I have also noticed some books which says "Index and Archive records". Can someone share your thoughts on this.

Thanks
Subbu
 

admin's picture

This question has been asked  before. Just search for  "release resources" on PMZilla and you will find the answer