How do you answer this
Submitted by vikasmisra on Sat, 04/07/2012 - 19:38
In your project, there have been several changes in the cost and schedule estimates, and the original estimating assumptions are no longer valid.
Calculate the estimate at completion (EAC) for your project based on the following data?
BAC = $ 300,000 AC = $ 100,000 EV = $ 150,000 CPI = 1.2 ETC = $ 120,000
According to me it should be BAC/CPI. What do you guys think
Forums:


swaroopk
Sat, 04/07/2012 - 19:58
Permalink
EAC=AC+ETC
In the question its given "Since original estimating assumptions are no longer valid", so I guess it's
EAC=AC+ETC
= $100000 + $120000
= $220000
vikasmisra
Sat, 04/07/2012 - 20:17
Permalink
Thanks Swaroop,Isnt
Thanks Swaroop,
Isnt EAC=BAC/CPI applied in a scenario where the original assumption are not valid.
I guess it doesnt say that current CPI is going to continue, it just says that you are running behind (or ahead) and hence use the formula EAC=AC+ETC.
Any suggestions
projmanpro
Sun, 04/08/2012 - 22:16
Permalink
From where did u take this
From where did u take this question?
My analysis of the question is - THIS IS NOT A TYPE OF QUESTION THAT MUST BE IN THE PMP EXAM, but this question could be an instruction or training sample question, as this question may have three calculations depending on how the situation would be.
In worst scenario, it this question appears in the actual PMP exam, i will solve this question, disregarding the situation given, and instead calculate based on the given data. Hence, the 3rd formula to be used.