Help on this Question

I am confused on this question need help.

Question : Resource Requirement is determined ?

Ans : Resource Requirement r determined after the network diagram is created and before Poject schedule. This is the question of PM FastTrack.

Y I am confused : I have the ITTO chart and when I see in the Planning section Scope and Time both comes before the Human Resource so how can that be an answer.

OR

Is it the case that the requirements are determined early and execution to fullfill those requirements are done in the human Resource section ?

admin's picture

Yes Requirement and fulfillment are different tasks. Requirements is done early before project schedule. 

akbar.azwir's picture

The question refers to a process called "Estimate Activity Resources" which is done after we "Sequence Activities". The resource required by the activity will be an input to human resource planing and procurement planning process.

 

Be sure to check out the PERT Calculator (link is external) and Earned Value Calculator (link is external) at my site.