Have to calculate PV or NPV for exam?
Submitted by ireskier on Wed, 02/27/2013 - 18:45
Crowe, How to Pass on your First Try says on pg 44 'Note: that you are no longer required to calculate PV or NPV for the exam'. Says you just need to remember that bigger is better. Yet I keep seeing the forumulas in lists of things to memorize for the exam.
Have any of you had to perform those calculations on the exam recently? Would love to NOT have to memorize that one. Thx.
Forums:


diba_perfect
Wed, 02/27/2013 - 19:37
Permalink
PV & NPV calculations are not
PV & NPV calculations are not required to be performed in the actual PMP exam.
~ Diba
ireskier
Wed, 02/27/2013 - 20:39
Permalink
That is music to my ears -
That is music to my ears - thank you! Taking the exam Friday, and stressed with working full-time and trying to cram. Every little bit helps. Thanks again.
pankaj_monga
Thu, 02/28/2013 - 09:27
Permalink
It is required. I took exam
It is required. I took exam on Feb 25 and there was one question to calculate NPV for three year horizon.
prakharsidana
Thu, 02/28/2013 - 06:20
Permalink
its required
Hi ,
We are still required to calculate this in the exam. I got couple of questions on this in my exam earlier this month.
Thanks
Prakhar
ireskier
Thu, 02/28/2013 - 12:25
Permalink
Guess I better expect NPV and
Guess I better expect NPV and study for it. Mixed messages if the prep books are telling us we don't need it, yet it's in some versions of exam. Thank you.
sunitaPMP
Tue, 03/05/2013 - 02:20
Permalink
So we need to know how to
So we need to know how to calculate NPV in exam?Please let me know.I have my exam on 17th March.
mercurie
Thu, 02/28/2013 - 06:30
Permalink
Rita advises us that it will
Rita advises us that it will not appear in the exam.
I have faced questions on PV calculation on many mock tests, but not in my PMP exam.
I made a mistake in the calculation for the mock test, as I used the given rate of 10%, as 10 itself in the formula. We should use it as 0 .1
PV= FV/(1+r) raised to n
If the rate is 10%, it should be FV/(1+0.1)... NOT FV/(1+10)
With hindsight, of course it is common sense that the denominator cannot be 11, should be something slightly above 1. But common sense sometimes stops working while taking the exam;)
ireskier
Thu, 02/28/2013 - 12:31
Permalink
PV calculation
Good point, thank you for reminder. Truly can't imagine NOT making a mistake or two like this under pressure. Will see tomorrow ...
rattanw
Thu, 02/28/2013 - 13:34
Permalink
Well you dont need to be
Well you dont need to be overtly worried about it. Just remember the following with regard to PV / NPV
ireskier
Thu, 02/28/2013 - 16:23
Permalink
Ok, burned into brain!
Ok, burned into brain! Forging ahead, will post results of exam tomorrow :)
sspawar
Fri, 03/01/2013 - 00:04
Permalink
it is true if concept is
it is true if concept is clear, It will hardly be a hurdle.
It is elementary maths.
PV formula is nothing but a reciprocal of compound interest formula.
if you remember your school maths
FV (compunding amount) = P(1+ (r in percent/100)^n), here P = principle amount, and P*(r in percent/100)^n is compounding interest.
In case PV , we write :
P= PV = FV / P(1+ (r in percent/100)^n),
---------------------------------
NPV is simple as a net profit over pv of cash inflow - pv of cash outflow.
----------------------------
And I dont think it cant be asked in exam.
If I ask - what is today,s value of 1000 earned at the end of 2 year at 15 % interest per year.
in this question no any term like pv is given but concept and formula is the same.
-----------------------
problem arises when -questions asked in bigger size and in tricky language and in varieties.
like a table of outflow and inflow is given for 4 years -----bla ---bla