Free PMP Exam Sample Question
The following PMP® exam sample question is taken from the Free PMP Exam Simulator:
------------------------------
You are working at a steel manufacturing company as a project manager. There is a department called Welding and Fabrication in your company. You are getting ready to put together your project team and you want to see a hierarchical representation of how many welders are working for your company in the Welding and Fabrication Department. Which of the following illustrates this information?
A.) Work Breakdown Structure
B.) Organizational Breakdown Structure
C.) RACI Chart
D.) Resource Breakdown Structure
------------------------------
Hint: A welder is a resource. The project manager wants to see all welding resources in a hierarchical format.
------------------------------
All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.
Please click here for the correct answer and explanation.
Until next time,
Cornelius Fichtner, PMP
President, OSP International LLC - http://www.project-management-prepcast.com


rit_mis
Tue, 11/20/2012 - 00:54
Permalink
D
D.) Resource Breakdown Structure
Explaination :
Hint: A welder is a resource. The project manager wants to see all welding resources in a hierarchical format.
kumark
Tue, 11/20/2012 - 03:49
Permalink
option D- RBS
RBS has all human and other material resources.