Free PMP Exam Sample Question
All,
The following PMP® exam sample question is taken from
http://www.free-pm-exam-questions.com – The answer is at the very bottom:
——————————
PMBOK Section: Sequence Activities
Process Group: Planning Process Group
Question Type: Calculation
Knowledge Area: Time Management
Difficulty Level: Moderate
Question: "Activity / Duration / Predecessor
A / 4 / START
B / 3 / A
C / 1 / B
D / 5 / START
E / 4 / D
F / 6 / E
G / 2 / C,F
H / 4 / D
I / 2 / H
What is the duration of the critical path?"
A. 10
B. 11
C. 17
D. 18
Hint : Use PDM to calculate.
Reference: PMBOK4 – pg:138
——————————
All our free questions are updated to the latest PMBOK® Guide standard. Sign up here:
http://www.free-pm-exam-questions.com to receive the questions via email. We are a PMI Registered Education Provider.
Until next time,
Cornelius Fichtner, PMP
The Project Management PrepCast™ –
http://www.project-management-prepcast.com
The Project Management Podcast™ –
http://www.project-management-podcast.com
The answer is C.
Explanation: The duration of the critical path for the given data is 17. Hence choice C is correct while rest of the choices are incorrect.