Free PMP Exam Sample Qstion

The following PMP® exam sample question is taken from http://www.free-pm-exam-questions.com - The answer is at the very bottom:

------------------------------

The method of constructing a project schedule network diagram that represents activities and connects them to show the dependencies is known as:

A) Arrow diagramming method
B) Schedule network templates
C) Precedence diagramming method
D) Activity list

------------------------------

All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try it for 3 days. We are a PMI Registered Education Provider.

 

Until next time,
Cornelius Fichtner, PMP
The Project Management PrepCast™ - http://www.project-management-prepcast.com
The Project Management Podcast™ - http://www.project-management-podcast.com

 

 

The Correct Answer is C.

The answer could be either A or C. There is nothing in the question that suggest it is Activity On Node diagramming technique. The definition could very well suit Activity On Arrow technique too.