Hi..what could be the right answer?
Soliciting feedback from stakeholders is important to the success of a project. If the project manager does not include this as part of the project development process, she can encounter plenty of problems later. The process of soliciting feedback and incorporating stakeholder ideas into the project is called
-
A. Feedback loop
-
B. Buy-in
-
C. Progressive elaboration
-
D. Project approval
Forums:


krantikumar50
Mon, 11/28/2011 - 11:23
Permalink
The Answer is...
The answer is B.
This is the right definition for the term Buy-in.
Kranti