Few questions
Submitted by danielkoshy on Mon, 12/02/2013 - 15:21
1)If we have to choose between 2 projects Project A IRR of $45,000 and payback period 15 months and Project B of IRR $30,000 and pay back period 10 months, which one would we choose?
Forums:


Stakeholder
Mon, 12/02/2013 - 18:12
Permalink
Gi with Higher IRR
My gut feeling and recollection to Rita says you need to go with the higher IRR and ignore the period of return.
andrewrmunro
Mon, 12/02/2013 - 19:20
Permalink
I think you may be confusing
I think you may be confusing two seperate topics. IRR is expressed as a percentage, not as a value over time.
You are confusing this with NPV which years are not considered in the evaluation as the NPV factors that in already.
Stakeholder
Mon, 12/02/2013 - 19:37
Permalink
No confusion here
You made me look :-).
Please refer to page no. 120 and 121 (int. mgmt) of Rita PMP exam prep. 8th edition. It has given an example with two scenarios, company A and B with 21% and 15% IRRs respectively and opts for the first as it states to go with the higher IRR. It also mentions that calculating IRR is complex and requires aid of a PC ... etc.
Stakeholder
Mon, 12/02/2013 - 19:40
Permalink
MAde me look :-)
And yes the question does have a onfusion on IRR and NPV, NPV does mention period of return. Wonder if this is how the queston was mentione in a MOCK exam!
danielkoshy
Tue, 12/03/2013 - 04:10
Permalink
Thanks
Hi stakeholder, you are right, the IRR is indeed a percentage, got it mixed up with NPV. But the main concern was which factor (IRR or payback period) was more important in a decision. I believe that IRR is the deciding factor and that you can ignore the payback period. But just wanted to get feedback from other users. Thanks.