 You are a project manager for one part of a new programm in your organization. You are four months into a three-years project when your project team makes significant discoveries on your project. What is the BEST thing to do?

A) Makes certain the discoveries are included in the project lessons learned

B) Makes certain the discoveries are reported in the monthly status report

C) Makes certain you mentioned the discoveries at the senior management meeting in two months

D) Makes certain you tell the other project managers involved in this program about the discoveries at the weekly meeting

 

 D

because it may affect as a risk/opportunity to the other part of program.

other options are time bounded not having any significant impact due to this significant  discovery (identified risk)

LL is record not a effective communication.

 

 D is correct choice

I would say D as well for the following reasons:

1.  Choice A is reactive, not proactive

2.  Fellow project managers are best intended audience initally.

3.  Weekly meeting is first opportunity to formally update others.  Waiting a month or two months could significantly affect cost and schedule if/when things are changed.

Lets imagine that there is no info in the question that the project is a part of a program.

Would it affect the option?