EVM Formulas
Submitted by dinduboy on Sun, 05/02/2010 - 06:07
hi i have got a list of formulas for EAC in EVM and am not sure in which case you would use them;
please see and advise.
1) EAC = AC+BAC-EV
2) EAC =BAC/CPI
3) EAC= AC + [(BAC-EV)/(CPI*SPI)]
I have read PMBOK but it doesnt make much sense to me.
Thanks.
The PMP Guru
Sun, 05/02/2010 - 12:04
Permalink
EVM Formulas
Hi dinduboy,
Good Question and it's always confusing. Let me explain it and I hope you will understand.
1) EAC = AC+BAC-EVProject is A-Typical, Whatever has happened, Project will be on Budget.
2) EAC =BAC/CPI
If Cost Variance continues. Then use this Formula.3) EAC= AC + [(BAC-EV)/(CPI*SPI)]
Used when both Cost & Schedule performance are considered.I kept it short for understanding.
Kind regards,
http://thepmpguru.wordpress.com/
dinduboy
Sun, 05/02/2010 - 13:38
Permalink
much thanks for the reply :)
much thanks for the reply :)
The PMP Guru
Sun, 05/02/2010 - 14:44
Permalink
Wellcome
You wellcome dinduboy.
If you have something else on your mind, I will be happy to help.
Kind regards,
The PMP Guru