What is the BEST way to make an accurate forecasting of ETC?
EAC - AC
BAC - EV
Manual Forecasting of cost of remaining work.
(BAC - EV)/CPI
sspawar
Thu, 04/04/2013 - 10:37
Permalink
A
y0zh
Thu, 04/04/2013 - 13:58
It's Scordo question, and answer is:
Manual forecasting of costs for remaining work is generally the best means of generating an accurate forecast. [Project Cost Management]
Thu, 04/04/2013 - 14:47
my answer was based on
following concepts
EAC also may be estimated based on manual/bottom up/or non manual.
in place of manual , bottom up summation is the best in accuracy.
refer p 184- manual bottom up summation , EAC and ETC and AC
sspawar
Thu, 04/04/2013 - 10:37
Permalink
A
A
y0zh
Thu, 04/04/2013 - 13:58
Permalink
It's Scordo question, and
It's Scordo question, and answer is:
Manual forecasting of costs for remaining work is generally the best means of generating an accurate forecast. [Project Cost Management]
sspawar
Thu, 04/04/2013 - 14:47
Permalink
my answer was based
my answer was based on
following concepts
EAC also may be estimated based on manual/bottom up/or non manual.
in place of manual , bottom up summation is the best in accuracy.
refer p 184- manual bottom up summation , EAC and ETC and AC