EV Question
Submitted by AD on Sat, 04/27/2013 - 23:36
Please help me with this question:
In your project you had planned to have Tasks A, B & C completed already, however tasks A, B, C, and D are 100%, 80%, 0%, and 0% complete respectively.
The value of each day of work is $100. Using the 0-100 Rule and the information given below, calculate the SPI:
Tasks A, B, C, and D have duration of 3, 5, 4, and 3 days respectively.
Ans. choices:
A. 0.25
B. 1
C. 0.50
D. 0.75
Forums:
mndasari
Sun, 04/28/2013 - 07:17
Permalink
IMO,PV for A,B,C is 3+5+4=12
IMO,
PV for A,B,C is 3+5+4=12 days and EV is 100% of 3 + 80% of 5 + 0% of 4 = 7, so SPI = 7/12 = 0.58
But dont see this answer in the options :(
Mahmoud Yassin
Sun, 04/28/2013 - 15:14
Permalink
EV
take care he said rule (0-100)
EV= 3*100%+0=3
sspawar
Sun, 04/28/2013 - 09:58
Permalink
http://pmzilla.com/confusing
http://pmzilla.com/confusing-questions-and-answers
see q 3 explained
Hemant Tandon
Sun, 04/28/2013 - 20:02
Permalink
There are multiple rules for
There are multiple rules for deciding the percentage complete:-
For solving the question, we need to apply 0-100 rule.
Now, as mentioned in the question, you had planned to have tasks A, B and C completed. So,
PV = PV of Task A + PV of task B + PV of task C
---PV = 3 * 100 + 5 * 100 + 4 * 100
---PV = 1200
EV = EV of task A + EV of task B + EV of task C
---EV = 3 * 100 + (Task B is only 80% complete, and as per 0-100 rule, the %complete of this task is 0) + 0
---EV = 300 + 5 * 0 + 4 * 0 = 300
SPI = EV/PV = 300/1200 = 0.25
So, the answer is A.
Regards,
Hemant, PMP
crushPMP
Mon, 04/29/2013 - 03:29
Permalink
+1
+1
Keithudson
Mon, 11/25/2019 - 09:21
Permalink
Reader
EV question is here. I want moer answers from you and i want to know how much information all of you just have these question from https://www.aussiessay.com/assignment-help.php site. Maybe you have answer and you won this quiz all the time.