EstimateProbability of project

Hi,

This is a question i have taken from the mock test.I am just looking for clarifiation in detail.If any one knows please share in this forum.

 

During the conceptual phase of pipeline project,the project engineer estimates the following.The cost of the materials to be most likely $100,000,optimistically $90,000 and pessimistically @120,000.The cost for labor most likely $80000.optimistically $70,000 and pessimistically $100,000.The cost for equipment most likely $60,000,optimistically $50,000 and pessimistically $70,000.The cost for construction management fees most likely $30,000,optimistically @20,000 and pessimistically @40,000.
What is the probability of project coming in under $ 2,70,000?

A. ZERO
B. Lessthan 50%
C. Exactly 50%
D. Over 50%
 

 


Activity

p

o

m

exp

 


 


 


 


p+6m+o/6

MAT


1,20,000


90000


100000


101666.67

LAB


100000


70000


80000


81666.667

Equip


70000


50000


60000


60000

Mana Fee


40000


20000


30000


30000

 


Total expected value


 


 


273333.33


ASKED VALUE


 


270000


Correct answer will be


 


Option B

 

Thanks pawar it is the answer.

With in 90 seconds or even 2 minutes of time duration shall we able to do this kind calculation.

Anyone who has come across such a kind of questions in the PMP Exam?

 

 

 I BELIEVE IT WOULD BE ONLY A PRACTICE QUESTION.

IT IS NOT A PMP QUESTION.

PMP WILL ASK IF , WILL BE A SHORT QUESTION.

---------------

Correction : formula written in main reply is incorrect p+6m+o/6, but calculation is done by correct formula (p+4m+o)/6