During Initiation Stage cost budget represented as ROE which is Conceptual level which refine during planning ( become preliminary) and execution and M&C (become definitive budget).
some of the mock test will give u different answer. I encountered this before and the answer given was -50 to +100 for ROM. But i suggest to follow the figure mentioned by cnppmp above.
I have provided the ranges as per the PMBOK, so you need to follow PMBOK, else you would answer wrongly...My advise for such things you need to follow the PMBOK blindly.
DonJuanin
Wed, 05/29/2013 - 17:16
Permalink
During Initiation Stage cost
During Initiation Stage cost budget represented as ROE which is Conceptual level which refine during planning ( become preliminary) and execution and M&C (become definitive budget).
Rmandal
Wed, 05/29/2013 - 17:26
Permalink
Values
Thanks..
I am looking for the range values...!!
DonJuanin
Wed, 05/29/2013 - 17:44
Permalink
http://pmp.groupsite.com/bet
http://pmp.groupsite.com/beta/discussion/topics/311421/messages
cnppmp
Wed, 05/29/2013 - 18:05
Permalink
Rough Order of estimate: -50%
Rough Order of estimate: -50% to +50 %
Budget estimate: -15% to +25 %
Definitive Estimate: -5% to +10%
Generally these are the etsimate terms used from PMP perspective.
Regards
CN Patil
ril
Sun, 06/02/2013 - 05:48
Permalink
mock test
some of the mock test will give u different answer. I encountered this before and the answer given was -50 to +100 for ROM. But i suggest to follow the figure mentioned by cnppmp above.
cnppmp
Sun, 06/02/2013 - 17:20
Permalink
For exam you ned to follow PMBOB
I have provided the ranges as per the PMBOK, so you need to follow PMBOK, else you would answer wrongly...My advise for such things you need to follow the PMBOK blindly.
Regards
CN Patil
MANOJ RAMRAOJI ...
Mon, 06/03/2013 - 14:09
Permalink
Range of estimates
based on various situations range of estimates can be used as below:
Rough Order of Estimate: + -50% OR -25 to 75%
Conceptual:-30 to 50%
Preliminary:-15 to 50%
Budgetary: - -10 to 25%
Definitive:+ -5% OR -5 to 10%
Final Estimate = 0