ES, EF, Free Float & Activity Duration.

 


Have read Ritas book and was able to follow along with the standard CP foreward and backward calculations. Working through the 101 PMPC math questions i am having a hard time understanding the questions for calculating ES, EF, Free Float & Activity Duration.


When reviewing the answers i understand the formulas, i am just having a hard time putting the logic all together. Does anyone know of a good video, drawing or other explaination for these processes.


I have watched Sir Ganttalots videos on Critical path but i must still be missing something.


Has anyone come accross a good resource that they think might help me put this all together.


Thanks.