Earned Value Calculation
Q. Activity A is worth $200, is 100% complete and actually cost $200. Activity B is worth $75, is 90% complete, and actually cost $120 so far. Activity C is worth $200, is 75% complete, and has cost $175 so far. The total budget is $1000. What is the schedule variantce of the activities listed?
A. -$77.50
B. -$57.50
C. 0.84
D. 0.88
The answer given is B. How do we arrive at the calculation? I tried the below calculation
| Activities | Worth | %Complete | AC($) | PV | EV |
| A | 200$ | 100% | 200 | 200 | 200 |
| B | 75$ | 90% | 120 | 75 | 108 |
| C | 200$ | 75% | 175 | 200 | 131.25 |
| 475 | 439.25 |
PV = Planned%Complete x Project Budget
EV = Actual%Complete x Project Budget
SV = EV - PV
SV = 439.25 - 475 = -35.75
How is -$57.50 arrived? Kindly explain the correct calculation. Thanks


narendra1961
Wed, 05/25/2011 - 17:49
Permalink
Activities Worth %Com
niteshrs
Thu, 05/26/2011 - 08:22
Permalink
Thanks a lot !!
Thanks a lot !!