Early termination question
Bill is the project manager of an external project for a customer. The project is expected to take about a year to complete. Six months into the project, the customer informs Bill that the project needs to be scrapped. During which of the following processes would procedures be developed to handle early termination of a project?
|
The answer's C but I think its none of these. Early termination clauses are developed when contracts are developed or finalized....and it's not written here as a choice.
This question is from Scordo...anyone who can help me get this right please??? Appreciate it!
Prakash999
Sat, 12/22/2012 - 04:02
Permalink
Close Project or Phase
I would say answer is B.Close Project or Phase
Please check PMBOK Close Project or Phase process . which Set/Q# is this from Scordo?
Prakash999
Sat, 12/22/2012 - 04:02
Permalink
Close Project or Phase
I would say answer is B.Close Project or Phase
Please check PMBOK Close Project or Phase process . which Set/Q# is this from Scordo?
sspawar
Sat, 12/22/2012 - 17:25
Permalink
Later I went through the
Later I went through the book:
B - The Close Project or Phase process establishes the procedures to investigate and document the reasons for actions taken if a project is terminated before completion. [Refer PMBOK 4th Edition, page 100] [Project Integration Management]
miners
Sat, 12/22/2012 - 19:39
Permalink
Thank you!
Apologies....the answer was B and not C. I mistyped it. It was from Scordo Set # 15
Thank you for helping me out! Guess I uncovered a gap...
gpta_varun
Mon, 05/19/2014 - 12:44
Permalink
Why Not Close Procurements ,
Why Not Close Procurements , since this is an external project ?
Best Regards,
Varun
jpawl
Mon, 05/19/2014 - 17:40
Permalink
He is not buyer's PM
Bill is the seller's PM in this question. Procurements activities are performed from buyer's perspective.