EAC Formulae with SPI ?
Submitted by rjbuzzing on Thu, 07/04/2013 - 16:24
Can somebody tell me if this is a valid formulae in PMBOK 4th edition - EAC = AC +(BAC - EV) / CPI.
I can only find EAC = [AC +(BAC - EV) ]/ (CPI * SPI) on Pg 185 PMBOK 4th edition.