Duration calculation
Hello friends,
This question is also from oliverlehmanns 75 questions. This is regarding 32nd question, when I calculated the duration is coming as 39 days where as the answer shows 37 days.
I have taken FF-2 days as lead of 2 days and FS+3days as lag of 3 days. So I calculated the durations as 20(activity1)+10(activity2)+5-2(activity 3 has two days lead) + 6+3(as the activity 4 has 3 days lag) which comes to 39 days.
am I doing anythig wrong in calculation.
http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm
appreciate your help
Thanks in advance
Nag


roblis
Tue, 02/10/2009 - 17:36
Permalink
little mistake
Oliver questions are not that easy uh? But it's a good chance to improve skills.
I took a look and I guess you're talking about the previous question (31st) , right?
Activity 3 finishes 2 days BEFORE activity 2 (it's a finish-to-finish relationship). As activity 2 has 10 days, activity 3 is not included in the critical path (it's kind of swallowed by activity 2).
THUS, activity 4 starts 2 days before activity 2 finishes.
Activity 1: 20 days
Activity 2: 10 days
Activity 4: 6 days + 3 days (lag) - 2 days (due activity 3 constraint)
37 days.
nag_suresh
Tue, 02/10/2009 - 20:32
Permalink
Hi Thank you for the
Hi
Thank you for the update. but here when you say Finish to Finish relation ship between activity 2 to activity 3..
as per my understanding, activity 3 will not be finished until activity 2 finishes. so as per this, first activity 2 will be finished which is 10 days. next activity 3 will be finished.
I am still not convinced with the explanation. could you please clarify where I m wrong?
Thanks,
Nag
roblis
Tue, 02/10/2009 - 21:43
Permalink
.
It's the opposite.
Activity 3 must finish 2 days before activity 2 finishes (FF - 2). The minus sign indicates that sucessor activity is going to finish first (it's a lead). If you had a plus (+) sign, the activity is going to finish after (it's a lag). If nothing is said, both activity will finish the same time.
I guess you're confusing leads and lags because it's a Finish to Finish. You must add or take them from the FINISH of sucessor activity.
If you're talking about Finish to Start, you add or take them from the START of the sucessor activity.
Better now or still in doubt?
nag_suresh
Sun, 02/15/2009 - 17:52
Permalink
Hi Robis Thanks a lot.
Hi Robis
Thanks a lot. Now I am clear about FF relationship.
Thank you very much for the detailed explanation.
Nag