duration and schedule problem

 Activity A = 4days, B = 3 days, C=7days, D=5days and E=3days. A is predecessor of B and C, E is successor of B and D, C is predecessor of D. There is a lag of 3 days between C and D. There are 2 non working days.What do you see from this data?

A) Duration is 22 days

B)Schedule is 19 days

C) Duration is 24 days and schedule is 22 days

D)Duration is 22 days and schedule is 24 days

 

Answer is D

 

Can someone explain as to how to solve this problem?

crushPMP's picture

NWD = Non-Working Day's can be inserted anywhere in the path, for simplicity I have inserted them at the end.

Path-1: A-B-E-NWD === Schedule = 4+3+3+2 = 12 ==== Duration = Schedule - NWD = 12 - 2 = 10

Path-2: A-C-LAG-D-E-NWD ==== Schedule = 4+7+3+5+3+2 = 24  ==== Duration = Schedule - NWD = 24-2 = 22

Path-1 is non-critical - Ignore

Path-2 is critical path - Becomes the Ans = D

 


           

14


19

     
     

4


11


FS+3(C to D)


 


D/5

 

   
     

 


C/7

 

 

 

 

 

0


4

 

 

 

 

   

 

 
 

A/4


 


 

   

 

   

19


22

   

4


7

 

 

   

 


E/3

     

 


B/3


 

 

 


 

 

                   
                     
       

so duration of project is 22 days

     
       

and 2 non working days if added any where

       

schedule will be 24 days

     
       

like your semester paper (exam) days are 10

       

but there is 4 days gap

       
       

then dur = 10, sche = 14