diff between resource calendar and resource histogram
Submitted by Sree on Sat, 02/23/2013 - 03:40
hi all...
Can somOne help me with the difference on resource calendar and resource histogram. And if possible the example pic thanx sree
Forums:


sspawar
Sat, 02/23/2013 - 05:36
Permalink
HISTOGRAM - 9.1.3.1 P224One
HISTOGRAM - 9.1.3.1 P224
One tool for charting Human resources is called - Resourse HISTOGRAM. It contains bars as resourse hours needed for particular period (shown at x axis). One Horzontal line , which shows possible maximum hours available continuesly for a project time.
CALENDAR
6.3.1.3 ---- it idescribes all human, equipment , and material , potentially available for planned activiries during project. It describes when and how these resources will be available during project.
Read complete 6.3.1.3
Sree
Sat, 02/23/2013 - 06:42
Permalink
thank you pawarji
thank you Pawarji
sunitaPMP
Sat, 02/23/2013 - 22:52
Permalink
Hello pawarji,I have one
Hello pawarji,
I have one question here.
If we consider resource calendar mentioned in 9.2.3.2 , is that same as resource histogram?
because here resource calendar with regard to project team member and not other resources like equipment etc.
Please clarify
sspawar
Sat, 02/23/2013 - 22:59
Permalink
Resource Histogram is a part
Resource Histogram is a part document of Resource Calendar.