Critical Path Question
Submitted by chullan88 on Tue, 06/17/2014 - 19:33
Activity 1 - Duration 4,starts immediately
Activity 2 - after act 1,Duration 8
Activity 3 - after act 2,Duration 5
Activity 4 - after act 1,Duration 8
Activity 5 - must take place concurrently with activity 3,Duration 3,starts after acts. 4 and 2
What is duration of critical path
18,15,17,12
Can someone show the network diagram for this??
Forums:


janlie
Wed, 06/18/2014 - 03:31
Permalink
Critical Path
Answer is 17
Critical path: S-1-2-3-E
Nabs
Wed, 06/18/2014 - 09:40
Permalink
start----- A1(4days)---------
start----- A1(4days)----------A2(8days)-------A3(5days)
\ \ \
\ \ \
A4(8days)-----A5(3days)-------- End
Path1: Start+A1+A2+A3+End= 17 days
Path2: start+A1+A4+A5+End= 15 days
Path3: start+A1+A2+A5+End= 15 days
Nabs
Wed, 06/18/2014 - 09:43
Permalink
oopps it removed all the
oopps it removed all the spaces. link A1 with A4 and A2 with A5. A3 will connect with End.
i hope i m not confusing you more.