CPIF

 A project is contracted as a Cost-Plus-Incentive-Fee (CPIF) type of contract. The project is negotiated such that if the final costs are less than expected costs, the sharing formula for cost savings is 75:25. The targeted cost is US$ 100,000 with an 8% incentive fee. If the project comes in at US$ 80,000, what would be the cost of the total contract?

This looks similar to the Scordo mock 11 - Q43 that I just worked. In it there were 3 components as follows:

- Actual cost = $80,000 +

- 8% incentive fee calced on the targeted cost = $8,000 +

- 25% sharing on the $20,000 difference saved = $5,000

Total = $93,000

Please do check my solution against his as I was not comfortable with it since it didn't quite fit the standard formula of PTA = Tgt. cost +(Ceiling Price - Target Price)/(Buyer's percentage share)

 

 I have solved the problem as follows and arrived at $138,000 which was wrong. please help me in understanding whether this is right way of doing i.e., taking target profit as 8% of target cost

Incentive = (Target cost - actual cost)* vendor's share ratio

= (100000-80000)*25/100= 5000

overhead fee=target profit + incentive

=5000+(8*100000)/100=13000

contract cost = overhaed fee +actual cost

=13000+80000=93000

 

Hwever the answer is $93000

cnppmp's picture

First calculate Final Fee:


Final Fee= (Target cost -actual cost) x 25% + Target Fee (8% of 100000)


                 = (100000-80000) x 0.25 + 8000


                 =20000 x 0.25 + 8000


                 = 5000 + 8000


                 = 13,000


So, Final Price = Actual cost + Final Fee


                           = 80000 + 13000


                          = 93000


 


Regards


CN Patil