cost overrun / underrun
Submitted by dipti1pmp on Thu, 11/13/2014 - 12:46
The most recent analysis of Microcorp's new fabrication facility renovation shows a CPI value of less than 1.0 What does this indicate?
A. The cost has overrun estimates.
B. The cost has underrun estimates.
C. The project is running ahead of schedule.
D. The schedule has slipped.
if cpi
Forums:


admin
Fri, 11/14/2014 - 03:45
Permalink
CPI greater than 1 is good
CPI greater than 1 is good (under budget):
< 1 means that the cost of completing the work is higher than planned (bad);
= 1 means that the cost of completing the work is right on plan (good);
> 1 means that the cost of completing the work is less than planned (good or sometimes bad).
In your case the cost has overrun the estimates.
Having a CPI that is very high (in some cases, very high is only 1.2) may mean that the plan was too conservative, and thus a very high number may in fact not be good, as the CPI is being measured against a poor baseline. Management or the customer may be upset with the planners as an overly conservative baseline ties up available funds for other purposes, and the baseline is also used for manpower planning.
dipti1pmp
Fri, 11/14/2014 - 05:35
Permalink
thanks admin
I got it now..:)
dipti1pmp
Fri, 11/14/2014 - 05:35
Permalink
thanks admin
I got it now..:)