cost management -- EAC
Submitted by vijayavadrevu on Sat, 03/23/2013 - 11:56
Jim performs a periodic analysis of his project. He notices the variances his project is experiencing are due to a one time unexpected expense. Considering the variances to date have been atypical, which formula should Jim use in calculating a revised estimate at completion (EAC)?
Ans is given as
EAC = AC+BAC-EV
How to arrive at this, from the formulae known, namely EAC = BAC / CPI and CPI=EV/AC?
Forums:


AP
Sat, 03/23/2013 - 12:26
Permalink
PMBOK 4th Edition Page 184
Typical - Some variances have occured and it is expected to continue in future too.
Atypical - Some variances have occured and it is not expected to continue in future.
Formulae:
EAC ‘fundamentally flawed’ = AC + ETC
EAC ‘Typical’ = BAC / CPI
EAC ‘atypical’ = AC + (BAC – EV)
EAC considering both CPI & SPI = AC + [(BAC-EV)/(CPI*SPI)]
vijayavadrevu
Sat, 03/23/2013 - 13:11
Permalink
Sir,can you please explain
Sir,
can you please explain what is meant by EAC ‘fundamentally flawed’
Regards
Vijaya
AP
Sat, 03/23/2013 - 13:32
Permalink
Invalid BAC
It means that while doing the BAC, there was some major flaw or discrepancy in calculation or assumption or any other factor which made the BAC to be deemed invalid. In such a case, the EAC will be the actual cost upto that point plus the bottom up ETC.
vijayavadrevu
Sat, 03/23/2013 - 13:44
Permalink
Thank You !!!
Thank You !!!